Construction Schedule Update

Hide Featured Image
false

Construction Markups Updated  September 28, 2020

9/28/2020 Construction Update Native Sun Distribution Project Schedule: This Week the crews will be finishing raw water line, tie-ins to existing system (top of Jenwood 9/28, and Gerka/Lady Lane Intersection 9/30.) Services: Services along Banner, Kenwood, Deer Ridge, Denwood, Jenwood, Lady Lane, Gerka. Testing: Testing for Denwood, Jenwood, Deer Ridge, Gerka, Lady Lane, and raw waterlines.