Construction Mark Ups 9-14-2020
Native Sun Distribution Project Schedule: This week, crews will be finishing connections to the existing system. Adding more appurtenances to the new pipe, and working mainline along Banner. They will also be testing the new system (flushing, chlorine, and pressure).
Crews will also be completing site work at both control buildings, and pouring concrete pads.